Subcontracting register (Spain)

The subcontracting log documents the chain of companies and self-employed individuals involved in a construction project under a contractor’s commission. It facilitates traceability and the communications required by Spanish regulations.

In short

Each contractor must have the logbook available when required and record any subcontracting before the start of the corresponding work. The logbook does not replace the safety plan or the incident logbook.

Content
  1. What is the book for?
  2. Who should have it
  3. What should be noted
  4. Relationship with subcontracting limits
  5. Access, communications and preservation
  6. Differences compared to other instruments
  7. Practical example
  8. Common mistakes
  9. Client, contractor and companies in the chain: distinct roles
  10. Subcontracting tiers and checks before work begins
  11. The exceptional additional tier: reasons, approval and notifications
  12. Liability: joint responsibility is not an automatic finding
  13. Official validation, retention and checking the real chain
  14. Related concepts
  15. On the blog
  16. References

AZ Dictionary

What is the book for?

The subcontracting log allows for the identification and tracking of successive contracts within a project and under a contractor’s commission. It is mandated by Law 32/2006 and further developed by Royal Decree 1109/2007. The information it contains helps to determine who is performing the work, for whom, and at what stage of the supply chain.

This is not a voluntary supplier registry or a site access list. Anyone entering the construction site may belong to a company whose involvement must be documented beforehand. The purpose of this logbook is to connect the administrative data with the actual activity that will be carried out.

Who should have it

The contractor required to maintain the logbook must obtain it from the labor authority corresponding to the work site, in accordance with the applicable procedure. This obligation is not automatically transferred to the health and safety coordinator, nor is it fulfilled simply because another company involved in the project has its own logbook.

In a project with multiple contractors, there may be separate logbooks for each contractor’s work. It is essential to clearly identify which work stream each contractor is responsible for documenting. While the subcontractor provides the necessary information and fulfills its obligations, this does not eliminate the contractor’s legally mandated responsibility for maintaining the logbook.

What should be noted

Subcontracting arrangements are listed chronologically and prior to the commencement of the corresponding work. The regulations stipulate information regarding the company or self-employed individual, the engaging party, the level of subcontracting, the subject matter of the contract, and the individuals responsible for organization and management, in addition to other preventive information included in the form.

Documentation is also required on aspects such as the submission of the relevant section of the health and safety plan, coordination instructions, and approvals for any exceptional extensions. The person responsible for health and safety coordination during execution and any changes in that appointment must be identified. The data is completed according to the regulatory template, not through informal selection.

Relationship with subcontracting limits

The book helps verify the position of each party involved and compliance with the subcontracting regulations. The regulations establish limitations and specific scenarios that must be analyzed before authorizing a new link in the chain. Registering a company does not legalize a subcontract that violates applicable requirements.

Exceptional extensions require the legally established conditions and procedures. They should not be used as a routine mechanism to address insufficient planning. When specific approval and notification are required, the justification must be maintained and carried out within the established timeframe. Traceability ensures that the actual and documented supply chains do not evolve separately.

Access, communications and preservation

The book must remain on site throughout the execution of the project, as stipulated. The regulations recognize access for the parties entitled to it and require notification of each subcontract to the health and safety coordinator and, where applicable, to the representatives of the affected workers.

The contractor must keep it for five years after the completion of their participation in the project. In building projects subject to the regulations, a completed copy is given to the director de obra for inclusion in the building logbook, with the contractor retaining the original. Administrative closeout must provide for these obligations.

Differences compared to other instruments

The REA ( Registry of Accredited Companies) certifies certain company requirements; the subcontracting register documents the contractual chain for the particular works. The health and safety plan outlines the contractor’s preventive measures. The incident logbook serves to monitor and track the plan, with its own rules for recording and reporting.

A platform can help link this information, but an internal record should not be confused with the required regulatory instrument. The method of enabling and using it must comply with the procedure of the competent authority. Digitizing a copy does not, in itself, modify the obligations or the responsible parties.

Practical example

In a hypothetical example, a contractor brings in a company for one phase of the installations. Before starting, they check the planned subcontracting, obtain the necessary information, make the corresponding notes and communications, and organize the coordination. The company then proposes bringing in another entity for a portion of the work.

The proposal is analyzed before the entity begins: its position and applicable limits are reviewed, requirements are checked, and the ledger is updated as needed. There’s no waiting until the end of the month to reconstruct what happened. This way, the document helps control actual decisions and doesn’t simply describe a chain of events that has already been executed.

Common mistakes

The most common mistakes are making entries after the start date, mistaking the logbook for a personnel list, and assuming that the existence of a coordinator replaces the contractor’s responsibilities. Another mistake is forgetting to record changes in companies, representatives, or coordination that should be documented.

Effective management assigns a person responsible for keeping information up-to-date and establishes procedures for receiving proposals for new subcontracts. The review process should compare the written information with the actual work being done. The preventive and traceability value of the logbook depends on this correspondence and on adherence to its communications and deadlines.

Client, contractor and companies in the chain: distinct roles

Spain’s Law 32/2006 defines positions through the contractual relationship and the actual organisation of work. Under Article 3, the project client is the individual or legal entity on whose behalf the works are carried out; the contractor undertakes directly to that client to execute all or part of them using its own or other resources. Each contractor needs the register documenting its chain. Ownership alone does not make the client responsible for maintaining every contractor’s register. Nor should every company present be called a contractor without identifying who engaged it and what work it is undertaking.

A client that directly executes work using its own resources may also have contractor status. The Act includes specific rules for temporary business associations and self-employed people who employ workers. Royal Decree 1627/1997 also treats the client as a contractor in relation to directly engaged self-employed workers, with an exception for certain work commissioned by a householder on their home. These rules have particular scopes: they should not be transferred automatically between legal instruments without checking the activity, organisation and responsible party. Contract labels should be tested against the actual arrangement.

Appointing a health and safety coordinator when the conditions in Article 3 of Royal Decree 1627/1997 arise does not release the client from its responsibilities. Nor does it make the coordinator responsible for maintaining every company’s subcontracting register. A useful diagram identifies who engages whom, who executes the work, who makes entries, who receives notifications and who verifies preventive conditions. This is an organisational aid rather than a mechanism for transferring statutory obligations through a checkbox. The register, safety plan and coordination arrangements should describe the same real project.

Subcontracting tiers and checks before work begins

Tiers describe successive contractual links, rather than the total number of businesses that can be present on site. A contractor may engage several first-tier subcontractors; four companies operating in parallel do not, by themselves, demonstrate a breach of the tier limit. Review each branch from its contractor and identify the work actually assigned through each contract. An organisation chart without contracts or activity descriptions can conceal a different relationship from the one depicted. Headcount and badge records may support a review but do not determine contractual tier on their own.

Under the general Article 5 rules, contractors and first- and second-tier subcontractors may subcontract within the statutory conditions; a third-tier subcontractor may not subcontract again. Self-employed workers may not subcontract the work assigned to them. Restrictions also apply to subcontractors whose organisation deployed on the works fundamentally consists of supplying labour with the tools described by the legislation. Hiring a machine or renaming an agreement is not enough to conclude that the restriction disappears. The organisation actually deployed and the applicable legal definition need to be assessed.

Before a new company starts, check its position, applicable regime and relevant organisational, preventive training and accreditation requirements. The entry must precede the subcontracted work, rather than form part of a monthly reconstruction of site arrivals. In a hypothetical example, a second-tier company proposes that another business perform part of its assignment: that third tier and the incoming company’s conditions must be considered before work is authorised. If the incoming business then wishes to subcontract again, a separate assessment is required. Physical access permission does not remove a statutory limit or replace the necessary checks.

The exceptional additional tier: reasons, approval and notifications

Article 5.3 of Law 32/2006 allows a single additional tier exceptionally in the specified circumstances. The provision requires duly justified unforeseen cases in which specialist-work requirements, technical production difficulties or force majeure make the engagement necessary in the opinion of the project’s professional management team, the dirección facultativa. Its approval must precede the additional subcontracting and the reason must be recorded in the register. Schedule pressure or commercial preference should not become a generic explanation used without further assessment on every project. A documented decision should address the actual work and the circumstance relied upon.

The exception has additional limits: for the self-employed and predominantly labour-supply situations addressed in Article 5.2(e) and (f), it can only be based on force majeure. Software that allows another tier to be added without checking those conditions does not make the arrangement compliant. Distinguish the proposal, assessment, approval and register entry, retaining the professional management team’s decision. Documentary handling should reflect the real timing. Obtaining a signature later does not convert late approval into prior approval, and a platform status should not conceal that distinction from people reviewing the chain.

The contractor must notify the exceptional subcontracting to the health and safety coordinator and the worker representatives of companies within the execution scope of its contract that are identified in the register. It must also notify the competent labour authority within five working days of approval, providing the management team’s necessity report and a copy of the entry. These are specified recipients and deadlines, distinct from an internal platform notification. Follow-up should check that the communication occurred and contained the required information, rather than relying solely on an approved request status.

Liability: joint responsibility is not an automatic finding

Article 7 of Law 32/2006 requires contractors and subcontractors to monitor specified accreditation, registration and subcontracting requirements for the businesses and self-employed workers they engage. Information about those requirements must pass to the engaging business. Paragraph 2 provides for joint and several liability concerning employment and Social Security obligations within its stated circumstances and scope. It does not mean that every participant on a project automatically bears responsibility for every accident anywhere in the chain. The relevant duty, breach and legal regime must be identified before drawing a conclusion.

Administrative liability for prevention has its own framework. Article 42.3 of the Spanish Social Order Infringements and Sanctions Act concerns the principal undertaking and contractors or subcontractors under Article 24.3 of the Occupational Risk Prevention Act: the principal’s own activity, its workplace and the contract period, with the infringement occurring in that workplace. Those conditions must be established. A project client is not invariably the principal undertaking for this purpose. An administrative rule should not be extended to civil damages or criminal responsibility without examining the separate requirements of those regimes.

Investigation of an incident needs facts: who organised the task, what risk was known, what controls had been planned, which instructions reached the workplace and what checking occurred. The register helps identify participants and the contractual sequence but does not prove all these matters by itself. A coherent file links contracts, entries, communications and implementation evidence while preserving dates and versions. Investigators should not retrospectively complete the register as though it had always been current. A later documentary correction is not evidence that an earlier preventive measure was actually implemented.

Official validation, retention and checking the real chain

Royal Decree 1109/2007 requires the contractor to obtain the officially validated register before the first subcontract. It regulates replacement when the previous register is full or damaged and addresses loss or theft through a declaration and reproduction of the relevant entries. Where the register is required in judicial proceedings, the provisions on an authenticated copy before handing over the original must be followed. A spreadsheet can help prepare information, but it does not by itself replace official validation or the prescribed format. An internal database and the statutory instrument should remain clearly distinguished.

Every entry must precede the subcontracted work and be accompanied by the prescribed communications. The contractor keeps the register on site until its assignment is completed and retains it for five years after its participation in the works ends. For building projects within the Spanish Building Act’s scope, it gives the director de obra a completed copy for inclusion in the building logbook and retains the original. Administrative closeout should identify responsibility, location, access and retrieval arrangements. Filing a link that will stop functioning does not ensure continued availability of the document.

As an organisational check, a sample of active work can periodically be compared with recorded companies and tiers, start dates and notifications. Updating problems should be distinguished from material safety failures on site: correcting a company name does not remedy a missing safeguard or a hazardous interaction. Proposed new businesses need a process that operates before they start and an identifiable responsible person. The subcontracting register, Register of Accredited Companies and construction safety incident logbook fulfil different, complementary functions. Linking their evidence improves traceability without turning any one of them into a substitute for the others.

Related concepts

On the blog

References

  1. Official State Gazette. Law 32/2006, regulating subcontracting in the construction sector. Consolidated text. Official source
  2. Official State Gazette. Royal Decree 1109/2007, implementing Law 32/2006 on subcontracting in construction. Consolidated text. Official source
  3. Official State Gazette. Royal Decree 1627/1997, minimum health and safety requirements for construction sites. Consolidated text. Official source
  4. Social Order Infringements and Sanctions Act: administrative liability of the principal undertaking Primary source

Editorial information

Publication date: October 10, 2026.

Last updated: 8 November 2026.

Editorial Manager: Sabentis Editorial Team.

Author: Pablo Rodríguez LinkedIn

Executive Vice President of the ORP International Foundation and Chief Financial Officer of Sabentis.

Request a Demo

Discover all that Sabentis can do for your organization.

Try Sabentis

request a demo
stars 5
GetApp Software Advice Capterra