Spain · National · Order

Order ETU/995/2017: mining electrical installations

In force within the stated scope

Current official Spanish title: Orden ETU/995/2017, de 6 de octubre, por la que se aprueban instrucciones técnicas complementarias del capítulo IX "Electricidad" del Reglamento General de Normas Básicas de Seguridad Minera.

On this page
  1. What it regulates
  2. Who it applies to
  3. Key provisions
  4. History and versions
  5. Transitional provisions and application notes
  6. Official BOE legal relationships
  7. Official sources
  8. Explore the concepts in Sabentis Explore

What it regulates

Approves four instructions under chapter IX of the mining regulation: terminology, common rules, underground installations and potentially explosive atmospheres.

Who it applies to

IET-ITC 09.0.01–09.0.04. Applicability depends on whether an installation is new, substantially altered or presents a serious risk identified by the mining authority.

Key provisions

Covers new installations and their alterations and extensions. For earlier installations, substantial repairs or alterations affect the part worked on, without automatically subjecting the entire installation to the new regime.

Article 2

Work affecting more than 50% of installed power, complete lines, new circuits or switchboards is substantial, even if power is reduced. The authority may require adaptation where there is serious risk through a reasoned decision.

Article 2

Common requirements are supplemented by specific rules for underground workings and explosive atmospheres. Design, protection, earthing, documentation, commissioning and maintenance must be checked for the installation concerned.

IET-ITC-09.0.02

The inspection regime applies to all installations. For earlier installations outside the adaptation cases, technical inspection criteria remain those of the regulations under which they were approved.

Article 3

History and versions

Initial publication: 17/10/2017 · Initial entry into force: 17/10/2018

BOE-A-2017-11908

Published on 17 October 2017; instructions applicable from 17 October 2018. The checked record lists no subsequent amendment or repeal. The transitional regime for existing installations remains relevant.

All text versions recorded by the BOE

Publication and effective dates are different. The table retains the dates and provisions of each recorded text version; it does not treat future transitional deadlines as requirements already applicable.

Transitional provisions and application notes

  • The new instructions entered into force on 17 October 2018, one year after publication on 17 October 2017. Publication must not be used as their general obligation start date.

    Final provision third
  • The transitional provision preserves the listed earlier ITCs for existing installations to which the new instructions do not apply. The order therefore does not indiscriminately repeal all earlier electrical ITCs.

    Transitional provision sole

Official BOE legal relationships

Relationships may affect only specific provisions. They do not by themselves determine the status of the whole instrument: consult its history and application notes.

Earlier references (4)

Official sources

Official sources checked on 14/11/2026. Updating a database record does not by itself mean that the legislation has been amended.

  1. BOE-A-2017-11908
  2. BOE-A-2017-11908
  3. ELI identifier

Official sources checked on 14 November 2026. Consolidation, where available, is informative and has no legal force. Consult the official publication and check the applicable provision and date.

Sabentis editorial translation into English; it is not an official translation and does not replace the official text.

Editorial information

Publication date: 14 November 2026.

Editorial responsibility: Sabentis editorial team.

Editorial review by Pablo RodríguezLinkedIn

Executive Vice President of the International ORP Foundation and Chief Financial Officer of Sabentis.

Request a Demo

Discover all that Sabentis can do for your organization.

Try Sabentis

request a demo
stars 5
GetApp Software Advice Capterra