On this page
What it regulates
Approves surface-mining instructions on personnel safety, project design and development of workings. The entry highlights preventive organisation, training, safe access, supervision and project documentation.
Who it applies to
ITCs 07.1.01, 07.1.02 and 07.1.03 in RGNBSM chapter VII. This entry selects the OSH connection; it does not provide geotechnical design or universal dimensions for benches, berms, roads or slopes.
Key provisions
ITC 07.1.01. Organisation must assign safety functions through internal instructions. New personnel receive training appropriate to their role, and work must be supervised. Assignment requires the applicable fitness and competence conditions.
ITC 07.1.01ITC 07.1.01. Access, personal protection and workplace conditions must be controlled. Before restarting after a prolonged stoppage, supervisors check safety conditions; rockfall risks require inspection and preventive action.
ITC 07.1.01ITC 07.1.02. The mining project documents the working system, resources and conditions needed to assess safety. Prevention depends on deposit and ground characteristics and the project’s technical justification.
ITC 07.1.02ITC 07.1.03. Development of workings links mine design with stability, access and equipment movement. Maintenance measures and decisions about faces and slopes must be based on the project and actual conditions, with competent input.
ITC 07.1.03History and versions
BOE publication: 30/04/1990 · Initial entry into force: 20/05/1990
BOE-A-1990-9859Published on 30 April 1990; effective from 20 May 1990. The consulted consolidation shows the initial text, with no recorded later amendments or express full repeal. Its transitional provisions must be read against authorisations and projects at that commencement date.
Text versions of the selected OSH provisions
| Publication | Effective date | Official reference | Affected provisions |
|---|---|---|---|
| 30/04/1990 | 20/05/1990 | BOE-A-1990-9859 | Transitional provision first, Transitional provision second, Transitional provision third, Transitional provision fourth, ITC 07.1.01, ITC 07.1.02, ITC 07.1.03 |
Transitional provisions and application notes
The twelve-month period for submitting adaptations of certain existing workings is a 1990 transitional rule, not a newly open period. The exception in transitional provision four requires a mining-authority decision and a Mining Safety Commission report; it is not a unilateral operator exemption.
Transitional provision thirdTerritorial application: article 2 of Royal Decree 863/1985 distinguishes direct application of the ITCs, supplementary application in autonomous communities with regulatory powers, and regional rules. ITCs on standardisation and approval, and those on explosives, apply directly throughout Spain. The site’s regional rules must be checked.
Article 2
Official BOE legal relationships
This record covers the history of the selected occupational safety and health provisions. The official analysis also provides the relationships affecting other subjects in the legislation.
Official BOE legal relationships